This is a patch for trunk r10659. Taken from the MS Project functionality descrition: For the status date (today) of your project, it draws a progress line connecting in-progress tasks and tasks that should have started, creating a graph on the Gantt Chart with peaks pointing to the left for work that is behind schedule and peaks pointing to the right for work that is ahead of schedule. The distan